Mumbai's Deonar Dumping Ground Faces Further Setbacks as Multiple Mega Projects Create Administrative Deadlock

user Admin
  • 15th Aug 2025
  • 1286
  • 0
Mumbai's Deonar Dumping Ground Faces Further Setbacks as Multiple Mega Projects Create Administrative Deadlock
Never miss any update
Join our WhatsApp Channel

Mumbai's decades-old Deonar dumping ground reportedly confronts another year of delays as overlapping environmental projects struggle with regulatory approvals and site constraints, according to recent administrative updates. The ambitious waste-to-energy initiative, initially conceived in 2022, continues facing hurdles amid mounting waste accumulation and administrative complexities.

Project Status and Extended Timeline

Officials revealed that the waste-to-energy plant, originally awarded in August 2022, has experienced delays extending beyond four years from its initial proposal stage. The facility was designed to process 600 tonnes of waste daily while generating 7 MW of electricity. Industry sources indicate that the site currently houses approximately 185 lakh tonnes of legacy waste spread across 311 acres, with an additional 51.3 lakh tonnes of untreated waste accumulated as of March 2025.

Convergence of Environmental Initiatives Creates Complexity

The dumping ground has become the focal point for three significant environmental projects operating simultaneously. Authorities disclosed that a bioremediation tender targeting 185 lakh tonnes of waste clearance over 110 hectares within three years is currently in its bidding stage. This runs parallel to the planned waste management initiatives including the waste-to-energy plant and a proposed bio-CNG facility designed to handle 1,000 tonnes of waste daily.

Project Target Capacity Purpose Current Status
Bioremediation Tender 185 lakh tonnes in 3 years Legacy waste clearance over 110 hectares Bidding stage
Waste-to-Energy Plant 600 tonnes/day Generate 7 MW power from waste Delayed
Bio-CNG Plant 1,000 tonnes/day Compressed natural gas production Planned

Industry Concerns Over Simultaneous Operations

Environmental experts expressed concerns about executing multiple large-scale operations concurrently at the same location. The site's history of methane emissions and frequent fire incidents raises questions about operational safety and project feasibility when multiple initiatives overlap.

Contractor Challenges During Pre-Bid Phase

During pre-bid meetings, potential contractors reportedly raised several operational concerns including the feasibility of completing bioremediation within the stipulated three-year timeline, availability of additional land for processed waste storage, requirements for environmental and CRZ clearances, and the need for designated nodal officers for project coordination.

Current Bidding Process and Participants

Financial evaluations for the bioremediation project are currently underway with three major companies in contention. Re Sustainability Ltd, Navayuga Engineering Ltd, and HG Infra Engineering Ltd have submitted proposals for the comprehensive cleanup initiative.

Urban Development Implications

The Deonar cleanup holds significant importance for broader Mumbai urban development projects. Municipal authorities indicated that clearing the dumping ground is essential for releasing 124 acres earmarked for the ambitious Dharavi Redevelopment Project.

Health and Safety Considerations

The landfill's waste mounds, reportedly reaching heights of 40 metres, continue releasing methane gas, creating fire hazards and respiratory health risks for surrounding communities. The facility has operated since 1927, making it one of Mumbai's oldest active dumping sites.

Learning from Previous Experiences

Past experiences at the Mulund landfill, where only 25 acres were successfully reclaimed over seven years, have heightened concerns about execution capabilities. Industry observers suggest that without robust implementation strategies and experienced technical partnerships, Deonar risks becoming another case study in delayed environmental projects.

Current Operational Status

Factor Detail
Landfill Age Operational since 1927
Total Area 311 acres
Waste Volume 185 lakh tonnes
Overlap of Projects Bioremediation, WtE, Bio-CNG at same site
Main Bottleneck Regulatory approvals, site constraints

Future Outlook and Strategic Recommendations

Administrative sources suggest that successful project completion requires clear sequencing of initiatives, streamlined approval processes, and strategic partnerships with experienced environmental technology providers. The success of these initiatives could significantly impact Mumbai's infrastructure development plans and environmental sustainability goals.

Disclaimer: This news article is based on available administrative updates and industry reports. Readers are advised to verify information independently and consult official sources for the most current project status and timelines.


Related Topics / Tags

Admin

Author

Admin

...


Comments

Add Comment

No comments yet.

Add Your Comment

Relevant Blogs

General
Pune Metro Line 3 Complete Guide: Red Line Route, Property Investment & Real Estate Impact

Pune's skyline is changing, and Metro Line 3 is leading this transformation. The Red Line, connecting IT giant Hinjewadi to bustling Shivajinagar, pro

General
Mumbai Housing Crisis: Complete Guide to Affordable Solutions and Government Schemes

Mumbai, India's economic powerhouse, faces one of the world's most severe housing crises. With over 2 crore people in the metropolitan region, the cit

General
Yugen Infra Brings Premium Goa Investment Options to Delhi-NCR Through Exclusive Property Expo

Yugen Infra announced its plans to organize a specialized property showcase in Gurugram on September 21, targeting investors interested in Goa's emerg