Central Railway Completes New Pedestrian Foot Overbridge at Sion, Sets Stage for Complete Demolition of Railway Overbridge Within Three Months
- 29th Oct 2025
- 1181
- 0
Never miss any update
Join our WhatsApp Channel
Central Railway has announced the successful completion of a new foot overbridge adjacent to the Sion railway overbridge, establishing a crucial pedestrian connection between the eastern and western sections of Sion. Officials confirmed that the footbridge has been opened to public use, enabling authorities to move forward with the complete demolition of the original railway overbridge, which is expected to be completed within the next three months.
Commuters Faced Significant Challenges Following Bridge Closure
Following the closure of the railway overbridge at Sion, commuters, particularly pedestrians, encountered considerable difficulties in their daily movements. The absence of a direct pedestrian route compelled local residents, including schoolchildren, college students, and patients visiting nearby medical facilities, to undertake lengthy detours. This situation sparked widespread opposition to the demolition plans until a practical alternative pedestrian facility could be established.
New Infrastructure Designed to Accommodate Daily Foot Traffic
The newly constructed foot overbridge measures 56 metres in length and 3 metres in width, having been specifically designed to safely and conveniently accommodate daily pedestrian movement across the area. With this facility now operational, Central Railway authorities can proceed with the remaining phases of the bridge's demolition, which forms part of a broader infrastructure upgrade plan for Mumbai.
Project Specifications and Timeline
The project is located adjacent to the Sion railway overbridge in Mumbai. The new infrastructure consists of a 56-metre by 3-metre foot overbridge dedicated to pedestrian use. Its primary purpose is to facilitate east-west pedestrian movement following the closure of the original bridge. The complete removal of the old bridge has been targeted for completion within a three-month timeframe. Officials cited infrastructure upgrades and safety concerns as the primary reasons for the demolition. The community impact has been significantly reduced due to the availability of the new footbridge for residents.
This development represents a significant milestone in balancing urban development requirements with commuter convenience in one of Mumbai's densely populated areas. Similar infrastructure initiatives across Mumbai continue to reshape the city's connectivity landscape.
Disclaimer: This news article is based on information available as of October 28, 2025. While every effort has been made to ensure accuracy, readers are advised to verify details independently. The views and information presented are for informational purposes only and should not be considered as professional advice. Infrastructure project timelines and specifications are subject to change based on regulatory approvals and execution challenges. Readers should consult official sources and relevant authorities for the most current and accurate information regarding this development.